Project Management Processes

Part 1

Save Time On Research and Writing
Hire a Pro to Write You a 100% Plagiarism-Free Paper.
Get My Paper

You have been assigned as a proje

c

t manager for a small construction company and have been assigned your first project. The client feels they have a basic grasp on their requirements but also feels that they will know more as the project progresses.  Using your knowledge of life cycle models, identify two models that may work based on your knowledge of the project.  

The scope of the project is as follows:

Save Time On Research and Writing
Hire a Pro to Write You a 100% Plagiarism-Free Paper.
Get My Paper

1. Requirement 1: 

3

bedrooms

1. Requirement 2:  2.

5

bathrooms

1. Requirement 3:  Pool 

1. Requirement

4

:  2 patios, one patio should be enclosed

Using your experience documenting scope, outline the problem/opportunity statement you are trying to solve for, 2-3 success criteria, and any assumptions, risks, or obstacles. 

Part 2

C

reate a Work

B

reakdown Structure (WBS) for the following scope:

1. Requirement 1:  3 bedrooms
1. Requirement 2:  2.5 bathrooms
1. Requirement 3:  Pool 
1. Requirement 4:  2 patios, one patio should be enclosed

Your WBS should be based upon your chosen Life Cycle Methodology and include any deliverables. 

Part 3

1. Build a network diagram

1.

I

dentify the early start, early finish, late start late finish for each activity

1. Identify the critical path

1. Identify the duration of the critical path

1. What is the float of

A

ctivity B

1. What is the float of Activity

H

Start

B

D

6

E

H

3

Activity

Predecessor

D

uration in Days

A

Start

3
B

6

c

A, B

12

D 5

E

4

F

C

G

E,F

8

H

7

I

Order a unique copy of this paper

600 words
We'll send you the first draft for approval by September 11, 2018 at 10:52 AM
Total price:
$26
Top Academic Writers Ready to Help
with Your Research Proposal

Order your essay today and save 25% with the discount code GREEN